beautypg.com

10 current reading zero calibration (r36), Current reading zero calibration (r36) -5 – KEPCO BIT 4882F User Manual

Page 25

background image

BIT 4882 030507

3-5

3. Turn the BOP “ON” and program the BOP Power Supply to ZERO CURRENT and MAXI-

MUM VOLTAGE LIMIT.

• If using SCPI send

FUNC:MODE CURR;:CURR 0;VOLT MAX

• If using CIIL send

FNC DCS:CH1 CURR 0 with VLTL 20

4. Locate Io COMP AMP ZERO control R83 (see Figure 3-1, refer to Table 3-1).

5. Adjust control R83 for zero, per Table 3-2, OUTPUT CURRENT ZERO.

6. Turn the BOP Power Supply “OFF”.

3.9

ADJUSTMENT OF THE FULL SCALE OUTPUT CURRENT (R22)

1. With the BOP Power Supply “OFF”, connect the PRECISION 4-TERMINAL SHUNT to the

power supply output terminals and connect the DVM to the PRECISION 4-TERMINAL
SHUNT (see Figure 3-2)

2. Turn the BOP Power Supply “ON” and program the BOP Power Supply for PLUS FULL

SCALE CURRENT and MAXIMUM VOLTAGE LIMIT.

• If using SCPI send

FUNC:MODE CURR;:CURR MAX;VOLT MAX

• If using CIIL send

FNC DCS:CH1 CURR zz with VLTL 20

where

zz

is the maximum rated output current of the BOP.

3. Locate CURRENT FULL SCALE control R22 (see Figures 2-1 and 3-1, refer to Table 3-1).

4. MEASURE the output current using the DVM. Adjust control R22 as needed until DVM reads

exactly FULL SCALE CURRENT per Table 3-2, FULL SCALE CURRENT ACCURACY.

3.10

CURRENT READING ZERO CALIBRATION (R36)

NOTE: The Output Current Zero Adjustment (PAR. 3.8) must be done before performing the fol-

lowing procedure, and the PRECISION 4-TERMINAL SHUNT should be still connected
to the power supply output terminals.

1. Program the BOP Power Supply for ZERO CURRENT and MAXIMUM VOLTAGE LIMIT.

• If using SCPI send

FUNC:MODE CURR;:CURR 0;VOLT MAX

• If using CIIL send

FNC DCS:CH1 CURR 0 with VLTL 20

2. MEASURE the output current using programming commands, then check the readback

data.

• In SCPI send

MEAS:CURR?

then check the readback data.

• In CIIL: send

FNC DCS:CH1 GAL

F0

INX CURR

FTH CURR

NOTE: For subsequent measurements using CIIL it is only necessary to send

INX

CURR

and

FTH CURR

commands.

3. Locate CURRENT READBACK ZERO control R36 (see Figures 2-1 and 3-1, refer to Table

3-1).

4. Adjust control R36 until the readback value is not 0.0 using MEASURE commands (see step

2) as needed.