beautypg.com

0 operation, 1 pressure cylinder filling procedure – Condec UPC5010 User Manual

Page 6

background image

Operation

3

2.0

Operation

The following sections explains the various procedures for operating the UPC5000/UPC5010.

2.1

Pressure Cylinder Filling Procedure

To initially fill or refill the internal pressure cylinder (2216 PSI max) of the UPC5000/UPC5010, see Figure 2-1
and proceed by following these steps:

1. Rotate the

PRESSURE LIMIT CONTROL

(1) counter-clockwise until it stops. Close the

COARSE

ADJUSTMENT

valve (2) by rotating clockwise until it stops.

2. Connect the fill hose (3), to a clean regulated nitrogen source (5).

3. Connect the other end of the fill hose (3) to the male fill port fitting (4).

4. Slowly open the valve on the nitrogen source and allow the gas to flow into the pressure cylinder. The

SUPPLY PRESSURE

gauge (6) indicates the amount of pressure within the internal cylinder.

NOTE:

The

Inlet Check Valve (PN 60263) and the Nitrogen Fill Port (Section 4.2.19 on page 25; Figure 4-3 on page 35)

can be damaged if pressure is released too fast.

5. Use the following procedure for filling the cylinder:

a) Fill cylinder to 1,000 PSI at a rate of charge equal to a minimum of two minutes, then wait five

minutes for system to stabilize.

b) Fill cylinder from 1,000 PSI to 2,216 PSI at a rate of charge equal to a minimum of two minutes.

c) Wait five minutes for system to stabilize before using.

Figure 2-1. Pressure Cylinder Fill Procedure

NOTE:

UPC5000 shown, AC Input (7) and Fill Port (4) are on back of UPC5010 Rack Mountable Calibrator.

This manual is related to the following products: