CT-7000 Operating Instructions

55

9.15 Print a Breaker Test Plan Directory

The CT-7000 breaker test plan directory stored in the CT-7000 EEPROM using the steps in

table below:

Table 19.0 Print a Breaker Test Plan Directory

STEP

OPERATION

ACTION

DISPLAY

1

SELECT SET UP MENU.

PRESS # 3 KEY.

1. ANALYSIS POINT

2. MEASUREMENT UNITS

3. SAVE / RESTORE

4. NEXT PAGE

2

SELECT ANALYSIS POINT.

PRESS # 1 KEY.

1. OPEN TIMING

2. CLOSE TIMING

3. PRINT SETTING

4. TEST PLAN

3

SELECT TEST PLAN.

PRESS # 4 KEY.

1. LOAD TEST PLAN

2. PRINT TEST PLAN

3. PRINT DIRECTORY

4

SELECT PRINT DIRECTORY.

PRESS # 3 KEY.

1.TIME BRKR

2.GET RSLT

3.SET UP

4.DIAGNOSTIC

Figure 24.0 Typical Test Plan Directory Print Out.