CONCRETE
PAD
DEPTH REQUIRED
BY LOCAL CODES OR
BELOW FROST LINE
2" TO 4"
ABOVE GRADE
1/2" RED HEAD BOLTS
0R ANCHORS (4 REQUIRED)
POWER AND CONTROL WIRING
SHOULD BE RUN IN SEPERATE CONDUIT
USING SUITABLE
HARDWARE SECURE
OPERATOR TO L-BOLTS
PAD MOUNTING (SW490)
NOTE: For the following instructions refer to figures 1
& 2 and SW490 gate installation table below.
1. Measure the gate length and select appropriate
“P” dimension from the gate installation table.
2. Layout the concrete pad as detailed in figure 1.
IMPORTANT NOTE: The relative location of the oper-
ator to the fence and the gate is critical. Be sure that
the measurements for operator mounting are taken
from the centerline of the fence and of the gate hinge.
3. Locate electrical conduit, as required, prior to pour-
ing concrete.
4. Pour concrete pad.
5. Bolt the (2) pad mount brackets to the bottom of
the operator with the hardware provided (Install the
operator so that the output shaft is on the side closest
to the gate).
6. Secure the operator to the pad. It is very impor-
tant that the operator be level and square to the gate.
FIGURE 1
FIGURE 2
SW490 GATE OPERATOR INSTALLATION TABLE
GATE LENGTH (FEET)
P DIMENSION IN INCHES
8-9
10-11 12-13 14-15 16-17 18-19 20-21
22
21.9
25.3
28.8
32.3
35.7
39.2
42.7
46.1