To find Follower Setpoint 1 (CP-03) for Example B:
Follower E.U. desired
Setpoint 1
=
________________________________
x
100 (%)
Lead E.U. operation
10 gal/min
The Follower Engineering Units (gallons/minute of ingredient B)
at which you want the Follower to operate.
Divided by
20 gal/min
The Lead Engineering Units (gallons/minute of ingredient A)
that the Lead is operating at.
Multiplied by 100 (%) Equals
50
Follower Setpoint 1 (CP-03) value.
To find Follower Setpoint 2 (CP-04) for Example B:
Follower E.U. desired
Setpoint 2
=
________________________________
x
100 (%)
Lead E.U. operation
7 gal/min
The Follower Engineering Units (gallons/minute of ingredient B)
at which you want the Follower to operate.
Divided by
10 gal/min
The Lead Engineering Units (gallons/minute of ingredient A)
that the Lead is operating at.
Multiplied by 100(%) Equals
70