Unload the X45 system

20

5113196-2

4

Unload the X45 system

4.1

Preparation

This section describes the steps that are required for unloading the mod-
ules for the X45 system.

Note! The operations concerned are to be carried out calmly in
order to be able to carefully monitor any movement of the X45
module.

Before starting the unloading a good preparation is required. The appropri-
ate devices must be available. Apart from that the first transport check is
an important part of the unloading, as in case of damage this should be
mentioned on the delivery note in relation to guarantee and the like.

The first transport check after arrival of the modules a transport check is to
be carried out. The check can be carried out at the moment the module has
been unloaded from the container or the truck. The technical specification
gives the dimensions to be checked. Is the module delivered undamaged
and is it the correct module?

.

Note! Any damage is to be mentioned on the delivery note and
should immediately be reported to the supplier. This with respect
to the guarantee of the module.

Module serial number type plate with
configurator string