Pipe Detail

Step 1

Cut on the proper pipe diameter

marked on the flashing.

Step 2

Position over pipe and

slide down the pipe.

Step 3

Apply polyurethane sealant

to the bottom of the base.

Step 4

Mold the flexible base

to the panel contours.

Step 5

Fasten with 1/4” x 1-1/8” drilling

fastener every 1-1/2” around

the base.

Pipe drawings provided by Triangle Fasteners

Tools and Rules:

Basic Equipment Required:
Tie-off ropes, safety harness, long level, ladders, scaffolding
with approved planking, extension cords with approved
ground plugs and services.

Additional Tools:
Metal folding tool, hammer, chalk line, measuring tape, metal cutting
tools - nibblers, drills, hacksaw, utility knife, pop-rivet gun, caulking
guns, layout and combination square, C clamps, sheet metal shears
(including RH, LH, straight and overhand). Power driven screw gun
with proper bits, depth-setting nosepiece, variable speed.

Choose the correct equipment and tools to do the job in a safe
manner. Wear safety gear and follow OHSA requirements.

Follow these simple rules:

1. Never cut the panels with an abrasive cut-off wheel or torch,

as this will damage the finish.

2. Do not weld the trim or panels.
3. Remove any small burrs left by cutting, screwing or drilling.
4. Remove protective masking immediately after trim is installed.
5. Caution should be taken when unloading the panels to

prevent damage.

6. Use appropriate screws for the type of underlayment and long

enough to fully penetrate and secure the panel.

7. The stored materials should be kept dry.
8. Do not cut on finished roof. Remove all drill spirals, chips

and dust immediately.

9. Seal neoprene closures and soft cell foam by applying

appropriate sealant to both surfaces.

10. Put appropriate sealant/butyle tape between overlapping trims.
11. Overlap trims in a manner not to impede the flow of water.

For further information or assistance, contact our Residential Product Support at 800-468-1441

©2007 Accel Roofing Products. All
rights reserved. Eco-Seam is a
tradename of ATAS International, Inc.

ATAS International, Inc.

www.atas.com ~ [email protected]

Corporate Office
6612 Snowdrift Road
Allentown, PA 18106

Sidewall Detail

1. Install ATA-Shield** at roof edge and

up face of sidewall. Install metal panel to
within 1” of the sidewall. Bend panel up
as shown.

2. Fasten “Z” closure in butyl tape on top of

panel as shown. Space fasteners at 6” o.c.

3. Fasten sidewall trim over “Z” closure to

face of sidewall.

4. Pop rivet sidewall to zee closure at 1 per length.

5. Apply counterflashing over the sidewall trim,

and seal into reglet.

NOTE: Trims should be fastened to substrate

using #12 x 1” wafer head screws.

Note Regarding Trim Details
The applicaiton of flashing and trim requires a detailed approach. Consideration should be given to the roof’s geometry and course it
creates for water run-off. Location of gutters and the use of snow retention systems should also be considered. Proper planning
regarding the sequence of material overlap is critical. Sealants, such as butyl tapes and tripolymers, should be used at overlapping
trim edges, in conjunction with exposed fasteners, and to seal flashings and other ancillaries. All fasteners should be properly
tightened and not overdriven at an angle. Fasteners that are too loose can “back out” over time. An overdriven fastener may cause a
depression in the material, which becomes a collection point for standing water.

Sealant

Appropriate Anchor Fasteners

Butyl Tape

#12 x 1” Wafer Head Screw

ATA-Shield

Eco-Seam Panel

ECO910 Zee Closure

ECO500
Sidewall Trim

ECO980 Counterflashing

LAC211