ATAS Advanta Shingle User Manual
Installation guide
Notch Panel 2”
Eave Side
Gable Side
Installation Sequence
12”
Typical
Setback
Panel Installation Detail
Snap a vertical line to square up the roof
plane with the eave line. Start in the
bottom left hand corner of the roof
plane with a full length panel. Install
shingles in a left to right manner
starting from the eave. Panel sidelaps
should be staggered with a 12-inch
typical setback. Repeat with a full length
panel every fourth row. Panels are pre-
punched to accommodate five fasteners
per panel. There are 170 fasteners per
square. Manufacturer recommends
using 2” ring shank, galvanized roofing
nails; however, a pneumatic fastener
gun with fasteners that have equivalent
pull out values can also be used. Screw
fastening may be utilized for increased
uplift resistance.
Installation Guide
Review and understand
complete guide before
beginning installation.
This guide has been prepared
as suggested details to
particular design conditions.
Each condition has certain
limitations to performance, aesthetics
or economics. Professionals qualified to assess the
information regarding suitability for a specific project
should determine that the selection and installation
are made to their requirements. ATAS cannot assume
any responsibility for the actual selection and/or
installation of materials. The panels, flashings and trim
shown in this guide, illustrated over solid and plumb
substrate, assume that the structure has been
designed and prepared in accordance with local
building codes.
ADVANTA Shingle’s patented four-way interlock design guards against wind
driven rain and prevents wind uplift. Panels measure 1’ x 3’ with a 3 square
foot net coverage area. There are seventeen (17) panels per carton and two
(2) cartons per square (100 square feet). Panels weigh 95 pounds per square.
Minimum recommended pitch is 3:12, subject to building codes.
**Recommended solid substrate is a minimum 5/8-inch exterior grade plywood or equivalent. Advanta Shingles can be applied over existing roofing materials
in accordance with local building codes. Current roof deck should be structurally sound and capable of anchoring fasteners.
Published panel width dimensions are to be considered as nominal dimensions. Overall panel width dimensions may vary during installation due to
adjustments to accommodate as built roof conditions.
®
Left Hand Shingle
(Applied First)
Right Hand Shingle
(Applied Next)
Solid Substrate**
Solid Substrate**
Upper Panel
Lower Panel
ATA-Guard*
2” Ring Shank
Grommeted Nail or
Screw Fastener for
increased uplift
resistance.
Left/Right End Lap Joint
Top/Bottom Lap Joint