4 single-phase, three-wire 120 v wiring, Ingle, Hase – GE Industrial Solutions EPM4500 Submeter User Manual
Page 20: Hree, 120 v w, Iring

CHAPTER 2: INSTALLATION
2-6
EPM 4500 SUB METER – INSTRUCTION MANUAL
WIRING
2.2.4 Single-Phase, Three-Wire 120 V Wiring
The phase association and polarity of the current transformers must be followed or
the meter will not be correctly installed.
1. Current transformers must be in-phase with the reference voltage. The MCI board
runs in an A-B-C phase rotation (see table below) and each of the three CT
connections repeat an A-B-C order.
For example, a current transformer installed in-phase with reference voltage A must
be installed on CT1, CT4, CT7, etc. Current transformers installed in-phase with
reference voltage B must be installed on CT2, CT5, CT8, etc. Likewise, current
transformers installed in-phase with reference voltage C must be installed on CT3,
CT6, CT9, etc.
2. For the “R” or residential 3-phase/3-wire model, each A-B, C-A, and B-C combination
is a single meter point (see the table below for full listing). That is,
3. – Meter 1 (M#1) is CT1 and CT2
– Meter 2 (M#2) is CT3 and CT4
– Repeated for M#3 to M#12
4. After completing all current transformer terminations, connect four (4) current
connectors and then remove the twenty-four (24) shorting links.
5. Follow all local codes for installation requirements; e.g. conduit, fused disconnect,
distance, and wiring.
6. Installation of “L” (0.1 A inputs) and “H” (CL10 or 5 A inputs) are the same. For the 3,
6 and 9 point models, use meter points M#1 to M#3, M#1 to M#6, and M#1 to M#9,
respectively. M#4 to M#12, M#7 to M#12, and M#10 to M#12 are not functional for
the 3, 6 and 9 point models, respectively.
If breakers are energized, shorting links must be installed before:
1. disconnecting the CT headers
2. replacing or installing meter heads on the panel.
Bodily injury may result if shorting links are not installed!