Site requirements, Operator and service access, Floor requirements – Kodak PROFESSIONAL LED II 20P User Manual
Page 124
Specifications
B-2
September 2000
Site Requirements
Operator and Service Access
When fully assembled the equipment requires a minimum of 91 cm
(36 in.) on each side to allow sufficient access for normal operator maintenance
and for service.
Floor Requirements
The equipment should be installed on a smooth, hard, and level floor surface.
Carpet is not recommended.
The floor pitch should not exceed 1 inch in 5 feet.
Printer
Processor
4.4 meters (174 in.)
2.9 meters
(114 in.)
15A
30A
1.5 meters (60 in.)
.91 meters (36 in.)
minimum
.91 meters (36 in.)
.91 meters (36 in.)
.91 meters (36 in.)
minimum
minimum
minimum
3.5 meters + .3 meters (138 in. + 12 in.)
2.2 meters + .3 meters (86 in. + 12 in.)
_
_
_
_
*
*
SCSI-2 connection from host here
4.5 meters (179 in.)