Page 17: Start-up, Leak checking, evacuation and start-up

background image

Parallel Compressor Systems Installation & Operations Manual, October 2004

17

Parallel Compressor Systems

Warning: It is illegal to knowingly vent or discharge

any CFC’s and HCFC’s to the atmosphere.

ALL CFC’s and HCFC’s must be reclaimed

or recycled.

Leak Check

1. To check the systems for leaks, leave all valves closed on

suction, liquid and hot gas manifolds. The unit is shipped

with a holding charge of dry nitrogen and should be leak

free. Build up the pressure in each circuit to a maximum of

150 psig dry nitrogen and check each individual circuit.

2. After each circuit has been checked, open all valves

to allow the pressure into the unit assembly. Check to

be sure pressure is throughout the assembly. Check all

connections and accessories for leaks.

Evacuation

1. After the system is leak checked, connect a good high

vacuum pump with fresh oil to both the low and high

side evacuation valves. Connections between the pump

and evacuation valves should be made with copper

tubing or high vacuum hose having a diameter of at least

3/8”. Evacuate the system to 1500 microns for the first

evacuation.

2. After each evacuation, the vacuum should be broken by the

introduction of refrigerant into the system. The refrigerant

should be passed through a drier when breaking the

vacuum until the pressure is brought up to 0 psig.

3. Between the first and second evacuation, the liquid

filter driers and suction filters should be installed in each

replaceable core shell.

4. A triple evacuation is recommended. The third and final

evacuation should achieve a value of 500 microns or less.

After this vacuum is reached, add as much refrigerant as

possible into the receiver. Now the system is ready to be

started.

Start-up

1. Set all pressure controls as recommended elsewhere in this

manual. Recheck all service valves and shut-off valves to

be sure they are open.

2. Check and be sure the condenser fan motors are running

in the correct rotation.

3. All evaporator fan motors should be checked for proper

rotation. The fans in low temperature boxes generally have

a fan delay for defrost purposes that keep the fans from

operating until the evaporator coil has reached a certain

temperature. It will be necessary to jump-out the fan

controls on freezer units to make them run through final

charging and room temperature pull-down. The wiring

diagram for the unit will have to be consulted to determine

how to best force the fans to operate for this step.

4. With all compressor and control breakers and toggle

switches turned off, apply power to the unit. If the unit is

using a phase monitor, the green light must come on before

going any further. (See instructions for phase protector

elsewhere in this manual.) A red light indicates incorrect

phasing or voltage. Check with a volt meter to see if correct

voltage is connected to the unit. Correct the Power Supply

before proceeding.

5. Turn on the circuit breaker for the control power. If an

electronic control system is installed on the unit, it will

initiate at this time. The Heatcraft preferred controller is

manufactured by Computer Process Control (CPC). Review

the manual for the controller supplied with the system.

6. Turn on circuit breakers to all compressors. The compressors

can be started by turning on the compressor toggle

switches. Likewise, each circuit control can be started by

turning on the circuit toggle switch. It is recommended that

one compressor at a time be started and checked before

allowing them all to operate. It is also advisable to check

one circuit at a time to be certain all components work

when called upon and that the circuit wiring is correct.

7. When each circuit and compressor has been tested and

the appropriate amount of refrigerant has been added for

proper operation, allow the system to operate and pull-

down the room/fixture temperatures.

8. Once the system is operating, set all regulating valves.
9. When the room and/or the fixture temperatures are

at design, the expansion valves should be set. (See

instructions elsewhere in this manual.)

10. Adjust the electronic or manual pressure controls

as necessary to maintain proper pressures and

temperatures.

11. Check the refrigerant level in the receiver. The minimum

level that should be maintained is 20%.

12. All circuit defrost controls must be set and checked. Again,

one circuit at a time should be tested.

13. Set condenser fan controls to maintain the proper discharge

pressure.

14. All safety controls should be checked and verified. Check

that the alarm circuitry is operating at this time.

15. Check the oil reservoir during the start-up and add oil as

necessary. The oil level should be between the upper and

lower reservoir sight glass. Do not add more than two

gallons of oil to a system. If more oil is needed, recheck the

piping as oil is not returning to the unit properly.

Leak Checking, Evacuation and Start-up