Memory Function

no function
default param.
reset Op.Data
Reset errors

No
function

Default param.: Sets all parameters to default.
Reset Op.Data: Sets all parameters that are
visible in user level to default values.
Reset errors: Resets all permanent device
disable (dBh) and the failure „EarthCurMax“
occurs. To remove this failure, follow the steps
in „Section 5: Commissioning the Sunny Boy“

Operating Mode

MPP-Operation
Turbine
V-const
Stop

MPP

Operating Mode of the Sunny Boy:
MPP-Operation: Maximum Power Point
Turbine: Operating mode for wind power
plants
V-const: Constant Voltage Mode (Setpoint
defined in „Vconst-Setval“)
Stop: Disconnection from utility, no operation

Pmax

W

0 ... 750

700

Maximum power output of the inverter

T-Start

s

5 ... 1600

10

The time the inverters waits to connect to the
grid after Vpv-Start is exceeded.
This value defaults to 5 minutes after a utility
fault.

T-Stop

s

1 ... 1800

2

Time that the Sunny Boy wait until it disconnects
from the grid.

Vac-Min *

%

0 ... 50

12

Lower (Vac-Min) and upper (Vac-Max) limit of
allowable AC voltage. Default value is optimal
for installations < 30 kW.

Vac-Max *

%

0 ... 20

10

Vac-Min-Fast *

%

0 ... 50

50

Lower and upper limits of allowable AC
voltage for fast disconnection. Default value is
optimal for installations < 30 kW.

Vac-Max-Fast *

%

0 ... 20

20

Vac-Min-Recnct*

%

0 ... 50

11.7

Values are used to calculate the lower and
upper limits to reconnect to the grid after a grid
failure

Vac-Max-Recnct

%

0 ... 20

5.83

Vconst-Setval

V

75 ... 330

275

PV Setpoint voltage for constant voltage
operation. These parameters only are
important in case the parameter „Operating
Mode“ is set to „V-const“.

Vpv-Start

V

125 ... 250

150

Voltage where the Sunny Boy starts connecting
to the grid.

Name

Unit

Range

Default

Description