CAUTION: To maintain UL Fire Classification, Slide Cover
must be replaced when communication cables
are removed. Order Cat.No. RC9SHTC.
CAUTION: Gasket must be set in place to provide scrub water
seal. Do not over-tighten Cover Mounting Screws.
Step 10 Communication Wiring
For cable pass-through, remove the egress
knockout located on the underside of the cover
Step 11 Attach Slide Cover with (2) #6 screws. Pass-
through cabling must pass through internal
gasket and data slide.
Step 12 Installation complete
Step 13 RC9 Less Junction Box
Cat No. RC9A15TC-LJB, and RC9A15TCLJB25
(Applies to installations in the City of Chicago
or other locations where local codes require
the use of a communication adapter, EMT
compression fittings, and a junction box
suitable for use in environmental air spaces.)
Follow Steps 1-11 for installation.
Pass-through
knockout
Slide Cover
Mounting Screws
(2) #6-32
Align Gasket over
Receptacle and press
bead into Flange.
Attach COM75 Adapter
(included with LJB Units)
per instructions supplied
with Unit.
Cut Slot in Gasket for
Cable pass-through
Once Poke-Thru is pushed into the cored hole,
from below, install an EMT compression fitting
(not supplied) and junction box to the conduit
system. Complete installation per NEC and