4
Slide Cover
Mounting Screws
Two (2) #6-32
Align gasket over
receptacle and
press bead into
flange channel.
Push Down
Once Poke-Thru is pushed
into the Cored Hole, from
below, install an EMT
Compression Fitting (Not
Supplied) and Junction Box
(Not Supplied) to the Conduit
System. Complete installation
per NEC and Local Codes.
Step 12
Attach slide cover with two (2) #6 screws.
Step 13 Push Poke-Thru unit into concrete to
complete installation.
CAUTION: Gasket must be set in place to provide
scrub water seal.
CAUTION: Poke-Thru cannot be rotated in hole after inserted
into floor.
Step 14 Installation complete.
Step 15
Follow steps 1 through 13 for installation.
AV3 Poke-Thru Less Junction Box
Cat. Nos. AV3ATC-LJB, AV3ARTTC-LJB,
AV3ATCLJB25, and AV3ARTTCLJB25
(Applies to installations in the City of Chicago or
other locations where local codes require the use of
EMT Compression fittings, and a junction box
suitable for use in environmental air spaces.)