Legrand FP-CTR User Manual
Page 3
3
Follow box instructions for a concrete pour. Once
concrete is cured, remove mudcap from boxes.
1
teRRazzo InstallatIon:
Attach FP-CTR flange and cover using the four (4)
#10-24 screws provided.
2
Pour terrazzo finish to top edge of flange and cover.
3
After the terrazzo has set and all floor polishing is
completed you can now continue the activation by
replacing the FP-CTR cover with a Floor Port Series
Cover (sold separately) and adjust height of cover
using the provided shims to ensure that cover is flush
with the flange edge.
4
note: fPfftc cover shown in illustration. fP-ctR
trim Ring also works with floorPort series
covers fPctc and fPbtc.