After Concrete Pour:
1.
Locate box and chip away concrete located on mudcap.
Remove mudcap. Clean out any debris (see Figure 3). If
further adjustment is needed after pour, adjustment is done
by turning adjusting ring counterclockwise using wrench
provided (see Figure 4).
2.
Route cables through to the box body.
3.
Remove cover and gasket. If required, connect receptacle
unit to the adjusting ring. Wire device in accordance with
the National Electrical Code or any local code that applies.
Make sure the ground lead is connected to the ground
screw before securing receptacle to adjusting ring (see
Figure 5). Install gasket and cover plate (see Figure 5).
Mudcap
Figure 3
Wrench
Figure 4
Gasket
825R2 Receptacle
825 Cover
Ground Wire
Ground Screw
Figure 5
© Copyright 2006 Wiremold / Legrand All Rights Reserved
Wiremold / Legrand
U.S. and International:
60 Woodlawn Street • West Hartford, CT 06110
1-800-621-0049 • FAX 860-232-2062 • Outside U.S. 860-233-6251
Canada:
570 Applewood Crescent • Vaughan, Ontario L4K 4B4
1-800-723-5175 • FAX 905-738-9721
1 000 273R1 – Updated February 2006 – For latest specs visit www.wiremold.com