beautypg.com

Legrand 800 Series Floor Boxes User Manual

800 series floor boxes, Before concrete pour

background image

Before Concrete Pour:

1. Determine box and conduit layout. Remove required knockout(s)

or plug(s). Attach proper conduit adapters (not supplied by Walker)
to steel base (see Figure 1).

2. Slip gasket over box assembly screws. Attach adjusting ring over

box. Align key slot with assembly screws and fasten ring to box.
Turn ring to lock in place and tighten screws (see Figure 1).

3. With wrench provided (supplied with 800LCK and 800CILCK)

attach conversion kit to adjusting ring (see Figure 2).

4. Using adjusting screws provided, adjust box so that top of box is

flush or slightly below screed line (see Figure 2).

5. Secure box to subfloor using wire or nails through the holes

adjacent to the assembly screws. Once positioned, connect
conduit to fittings (see Figure 2).

6. Place mudcap on adjusting ring (see Figure 2).

Gasket

Adjusting Ring

Key Slot

Assembly Screw

Conduit Adapter

Mudcap

Conversion Kit
(ordered separately)

Hold-Down Wire

Adjusting Ring

Conduit

Adjusting Screw

Figure 1

Figure 2

800 Series Floor Boxes

I N S TA L L AT I O N I N S T R U C T I O N S

Installation Instruction No.: 1 000 273R1 – Updated February 2006

Wiremold

®

electrical systems conform to and should be properly

grounded in compliance with requirements of the current National
Electrical Code or codes administered by local authorities.

All electrical products may present a possible shock or fire
hazard if improperly installed or used. Walker electrical products
may bear the mark as UL Listed and/or Classified and should
be installed in conformance with current local and/or the
National Electrical Code.

IMPORTANT: Please read all instructions

before beginning.

Products Covered: 800LCK, 800CILCK & 825CK Series

Warning: Pour concrete to 1/16" [1.6mm] above box housing.

Pours of 1/4" [6.4mm] or more over the housing will
make it difficult to breakout the mudcap and cause
excessive spading.