beautypg.com

14 connect the motor wires in the junction box, Verifying performance, 1 verify completion of the reassembly – Gasboy M06699KXXX User Manual

Page 7: 3 operate the unit and record the initial readings

background image

MDE-4541 Atlas™ Motor Kit M06699KXXX Installation • February 2006

Page 7

Installing New Atlas Motor Kits

12

Tighten the two shoulder bolts on the bottom of the deck plate.

13

Check belt alignment and tension. Readjust, if necessary.

14

Connect the motor wires in the junction box.

15

Ensure that the voltage on the motor is set correctly by checking the motor power select switch
in front of the motor. Adjust, if necessary. Refer to

Figure 3

.

Figure 3: Atlas Pump - Motor Select Switch.

Motor power select
switch - shown in low
voltage setting (110 volt
nominal)

Verifying Performance

1

Verify completion of the reassembly.

2

Connect the amp probe to a power leg of the motor.

3

Operate the unit and record the initial readings.

Parameter

Reading

Full Flow Amperage

Bypass Amperage

Bypass Voltage

Note: To maximize the flowrate, the pumping unit bypass valve spring preload will need to be

adjusted. The maximum allowable load on the new motor is 5.5 amps at 220 volts

(nominal) and 11 amps at 110 volts nominal.