beautypg.com

Tempest Cyclone User Manual

Page 23

background image



Cyclone Enclosure User Manual

page 23

4. Place the Christie Ballast in position and secure in place with the tie-down strap provided

5. Plug the ballast power cable into the 3-phase Ballast Power receptacle provided
6. Plug the two Camlok tails into the ballast. BE SURE TO TWIST CLOCKWISE to make a good

connection.

7. Connect the two Interlock cables to the Ballast D-Connectors.

8. Replace the Enclosure cover.
9. AUX POWER CONNECTION

a. Set the DEC3.3 wiring to Split Feed – see pp 18-19
b. Wire the AUX POWER output from the ballast to the SPLIT terminals on the DEC3.3

circuit board

c. Connect an IEC C13-C14 power cable between the receptacles on the side of the

DEC3.3 assembly to the AUX Power inlet on the projector head. This enables the

DEC to sense current to the projector when the head is active, running the fans

when needed. It also enables the DEC to shut down the projector in the event of a

catastrophic overtemp event.

Ballast

Tie-down Strap

Interlock

Connectors

This manual is related to the following products: