Rig the cabling, Check the assembly, Derig the ground stack – d&b T-Series User Manual
Page 34: T-sub/t10 ground stack, Limitation, Preparations, Order of assembly, Stack the two t-sub cabinets, Attach the first t10 cabinet
6. Rig the cabling
- Connect the cables and link cables according to the number of
amplifier channels and cabinets used.
7. Check the assembly
- Recheck the assembly according to the checklist given in section 5.
Checklist for the assembly of T-Series arrays on page 38.
8. Derig the ground stack
- To dismantle the ground stack, follow the assembly instructions in
reverse order. The same safety instructions apply.
4.2.2. T-SUB/T10 ground stack
Limitation
A maximum of 3 x T10 cabinets on top of maximum 2 x T-SUB cabinets
serving as ground support are allowed to be set up as ground stack.
Preparations
- Prepare the cables and link cables according to the number of
amplifier channels and cabinets used.
- Ensure the HF sections of the T10 cabinets to be used are set to Line
source.
Order of assembly
1. Stack the two T-SUB cabinets
- Interconnect the cabinets with their Front and Rear links.
2. Attach the first T10 cabinet
- Slide out the Front links of the T-SUB cabinet.
- Release the Locking pins at the front of the T10 cabinet.
- Attach the T10 cabinet to the Front links of the T-SUB cabinet.
- Insert and lock the Locking pins for the Front links on both sides.