Figure 29: Single-phase installation with 3 loads to connect (Load 1, 2 and 3 Connected).
As shown in
, we can see that although the inverter is 10 kW the
existing radiation only allows it to produce 9 kW, so to get 10 kW of consumption
it will have to take 1 kW from the grid.
In this situation the CDP-G maintains the system without adding or removing any
loads for the amount of time configured in the “Reconnection time” variable, in
order to achieve system stability (in this case 5 minutes).
• Disconnection condition:
𝑷𝑷𝑷𝑷𝑷
∑ 𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷𝑷 𝑷𝑷𝒓𝒓𝒓𝒓 < 𝑀𝒓𝒂. 𝑷𝑷𝑷𝑷 𝑷𝑷𝑷𝑷𝑷𝑷𝒐𝒐𝑷𝑷𝑷𝑷
(
1000
10000
= 10%) 10% ≤ 50%
this condition is met
relay 3 stays connected