CIRCUTOR CDP-0 User Manual
Page 28

CDP
28
Instruction Manual
4.3.2. SINGLE-PHASE INSTALLATION WITH 3 LOADS TO BE CONNECTED
We start with a single-phase installation in which we want to use the excess
photovoltaic production to supply 3 non-critical loads:
• Load 1: 2000 W water pump
• Load 2: 2000 W heat pump
• Load 3: 1000 W washing machine
The goal is to activate these loads during times in which there is a production
excess, thus reducing energy costs.
This is the baseline data:
PhaseP. Inverter Consumption Setpoint Current production
L1
10000 W
4000 W
40% 4000 W (40% of the nominal)
Figure 26: Single-phase installation with 3 loads to be connected.
The CDP-G programming is shown in
:
Loads
This manual is related to the following products: