Reznor UDBS Option - Installation - Separated Combustion Venting User Manual

Page 15

background image

Form I-UD-V-SC, PN195676R17, Page 15

THIRD, Install the Exhaust (Vent) Terminal.
Follow the instructions in FIGURE 2, page 5

.

SECOND, Install Combustion Air Inlet.

1) Slide the combustion air inlet over the vent pipe.

2) Fasten bottom of inlet to the combustion air pipe

with sheetmetal screws. Be sure not to penetrate

the vent pipe.

3) At the top, completely seal the space between

the vent pipe and the air inlet with silicone.

Double-wall V

ent Pipe

Cold Climate NOTE: In geo-

graphic areas where the design

ambient is -10°F or lower, this

minimum height is 24” (610 mm)

Single-wall Combustion Air Pipe

FIRST, If needed, add

a section of double-

wall pipe to reach

minimum height

requirement

Seal completely with

silicone to prevent

water leakage

FIGURE 16 - Install

Combustion Air Inlet

and Vent Terminal

9) Attach the indoor combustion air pipe. Use sheetmetal screws to attach the

single-wall combustion air pipe run to the collar on the concentric adapter box.

Seal with tape or sealant. If using 3” combustion air pipe on Sizes 30, 45, and 60,

install a taper-type reducer as illustrated in

FIGURE 7, page 7. Review Paragraph

1.7 concerning condensation; comply with all requirements that apply.

FIGURE 17 - Installation of Unit with Vertical Vent Terminal/

Combustion Air Inlet (Option CC2)

Rear

View

Side View

Installation of the vertical vent and combustion air system on your separated-combus-

tion unit is complete.

Verify compliance with all venting installation requirements,

pages 3-8, and FIGURE 17.