9.0 Commissioning

and Startup

Be certain electrical supply matches voltage of unit.

Check for proper grounding and polarity of the ignition system. The

direct spark ignition system cannot determine the presence of flame

if it is not electrically grounded to the burner; it will lockout and shut

off.

Clearance to combustibles must be maintained. (See Paragraph

4.2.) Check location of sprinkler heads; high temperature heads

may be required. Space directly below the heater should be free of

objects that may overheat or prevent infrared energy from reaching

desired area. Post signs indicating maximum stacking height under

or near heater.

Heater may be angle mounted only as specified. (See Paragraph

5.0.)

Heater must be level and suspended according to instructions in

Paragraph 5.0. Be sure there are no gas or electric lines above or

below the heater.

Adequate ventilation MUST be provided. (See Paragraph 2.2.)

Gas piping and supply must meet requirements. (See Paragraph

6.0.) Purge air from gas supply line.

Complete the installer record on page 20 and keep these instructions