4. Loosen belt tension and take belt off. See Fig. 20.
5. Remove bolt-belt adjustment assembly. See Fig. 20.

6. Move bolt-belt adjustment assembly to opposite side and

reattach. See Fig. 21.

7. Put belt back on and tighten. Put control box cover and

motor cover on return side. See Fig. 22.

8. Put 3 panels back onto unit. See Fig. 23.

Step 5 — Check Duct System —

The duct system

should be sized to handle the design airflow quietly.
NOTE: Depending on the unit, the fan wheel may have a ship-

ping support installed at the factory. This must be removed

before operating unit.
SOUND ATTENUATION — To eliminate the transfer of

vibration to the duct system, a flexible connector is recom-

mended for both discharge and return air duct connections on

metal duct systems. The supply and return plenums should in-

clude internal duct liner of fiberglass or be made of duct board

construction to maximize sound attenuation of the blower.

Installing the WSHP unit to uninsulated ductwork in an uncon-

ditioned space is not recommended since it will sweat and

adversely affect the unit’s performance.

To reduce air noise, at least one 90-degree elbow could be

included in the supply and return air ducts, provided system

performance is not adversely impacted. The blower speed can

be also changed in the field to reduce air noise or excessive air-

flow, provided system performance is not adversely impacted.
EXISTING DUCT SYSTEM — If the unit is connected to

existing ductwork, consider the following:
• Verify that the existing ducts have the proper capacity to

handle the unit airflow. If the ductwork is too small,

larger ductwork should be installed.

• Check existing ductwork for leaks and repair as

necessary.

NOTE: Local codes may require ventilation air to enter the

space for proper indoor air quality. Hard-duct ventilation may

be required for the ventilating air supply. If hard ducted venti-

lation is not required, be sure that a proper air path is provided

for ventilation air to unit to meet ventilation requirement of the

space.

Step 6 — Install Condensate Drain —

The con-

densate drain can be connected to either side of the unit. The

50VQP units come with a flex hose and 1 in. (25 m) FPT con-

densate connection tied inside. To install the condensate drain

(see Fig. 24.):

1. Untie the flex hose and make interal trap on either the left

side or right side of the unit.

2. Internally attach mounting plate with FPT fitting.

Fig. 20 — Remove Belt and Bolt-Belt Adjustment

Assembly

STEP 5

STEP 4

BOLT-BELT ADJUSTMENT ASM

a50-8482

Fig. 21 — Move Bolt-Belt Adjustment Assembly

STEP 6

a50-8483

Fig. 22 — Replace Belt and Motor and

Control Box Covers

CONTROL BOX
COVER

MOTOR
COVER

a50-8484

Fig. 23 — Replace Access Panels

FRONT RETURN TOP DISCHARGE

CONTROL
BOX

a50-8485