Hangar 9 3.1m Sukhoi SU-26MM ARF Assembly Manual

The picture below is of the tail end of the pipe tunnel.

5. Temporarily mount the pipe mounts and install pipes

to center the mounts before they are glued. Use lubricant on

the pipes for easier passage through the mounts when they

are not glued yet. Pipe mounts will not touch the floor of

the fuselage and need to be glued to the sides and bottom

former.

6. Once mounts are centered mark the spot on the sides

and formers.

7. Remove the pipes and use an acid brush to apply

30-minute epoxy to the sides of the mount and fuselage.

8. Reinstall the mounts and allow time for epoxy to cure.