Door-installation – Oldcastle BuildingEnvelope Reliance StormMax High Performance User Manual
Page 29
February 2014
27-Door-Installation
1-866-Oldcastle (653-2278) www.oldcastlebe.com
3.7 All door framing components are shipped fabricated from the factory. The main curtain wall framing can be
erected prior to installing the doors. Refer to FIGURE 3.7 for door header fabrication and installation
instructions.
a. Curtain wall verticals and door subframes run through to finished floor. Bed adjacent curtain wall verticals
in sealant and anchor to floor per approved shop drawings. See shop drawings for anchoring door
jamb mullion.
b. SUBFRAME INSTALLATION:
b.1 Assemble Door Subframe including TH-57 Threshold.
b.2 Install subframe into curtain wall frame. Shim plumb and true.
b.3 Anchor subframe with FS-322 space 18" O.C. Anchor threshold per shop drawings
b.4 Install door stops in subframe. The vertical stops run through.
b.5 Mask off frame with painter's tape and clean & seal perimeter of frame on exterior & interior
b.6 Install door per DOOR & FRAME INSTALLATION & GLAZING MANUAL.
ENTRANCE SUBFRAME INSTALLATION
FIGURE 3.7
Attaching Subframes
HW-500 Mullion
1/8" Shim Space
FS-322 Fastener 18" O.C.
D-226 Subframe
FG-5163 Door Stop
HW-122 Pocket Filler
Seal joint between vertical and
horizontal subframes
1/8" Shim Space
D-231 Door Head
RELIANCE STORMMAX HIGH PERFORMANCE INSTALLATION MANUAL