Multi-function Drill Control

38m

18 Bout Tramlining Sequence

This tramlining mode requires Great Plains P/N 890-785C NTA2000 dual tramline controls kit.

For use with a 20ft (6 meter) drill and a 90ft (27 meter) sprayer. (Two left hand seed spouts are closed on
bouts 3 and 16, and two right hand seed spouts closed on bouts 7 and 12). Starting on bout 1 requires turning
RIGHT at the end of the first bout.

NOTE: To turn LEFT at the end of the first bout, advance the bout number to 10 before commencing drilling.

The instrument will beep once at the beginning of each tramline bout and the display will flash for the duration