9.1 Closure commands for ramp segments
NEXT
Follow-on with next programme segment.
SPWT (T)
SET-POINT WAIT (temperature)
Wait until the setpoint temperature is reached.
The unit only starts the next programme segment when the programmed
setpoint temperature has been reached, even if the programmed heating
time has already elapsed.
SPWT (H)
SET-POINT WAIT (humidity)
Wait until set humidity is reached.
The unit starts with the next programme segment only when the
programmed humidity setpoint has been reached, even if the
programmed heating time has already elapsed.
SPWT (TH)
SET-POINT WAIT (temperature
and humidity)
Wait until set temperature and set humidity are reached.
The unit starts with the next programme segment only when the
programmed temperature setpoint and the programmed humidity
setpoint have been reached, even if the programmed heating time has
already elapsed.
LOOP
Ramp repeat function
The set programme is repeated after passing through all programmed
segments.
1-99
= repeats
cont
= continuous repeat function
HOLD
End of programme without switching off the heating and the humidifying
system.
END
End of programme, heating and humidifying system are switched off.
The programme segments are linked together by the segment closure command. These commands
therefore control the programme sequence.
Ramp
closure
command
ramp
segment 5
end
segment 5
°C
t=time
delayed
programme start segment 1
closure
command
ramp
segment 1
spwt (t)
segment 2
closure
command
ramp
segment 2
next
segment 3
closure
command
ramp
segment 3
spwt (tH)
segment 4
closure
command
ramp
segment 4
next