9.1 Closure commands for ramp segments

NEXT

Follow-on with next programme segment.

SPWT (T)

SET-POINT WAIT (temperature)

Wait until the setpoint temperature is reached.
The unit only starts the next programme segment when the programmed
setpoint temperature has been reached, even if the programmed heating
time has already elapsed.

SPWT (H)

SET-POINT WAIT (humidity)

Wait until set humidity is reached.
The unit starts with the next programme segment only when the
programmed humidity setpoint has been reached, even if the
programmed heating time has already elapsed.

SPWT (TH)

SET-POINT WAIT (temperature
and humidity)

Wait until set temperature and set humidity are reached.
The unit starts with the next programme segment only when the
programmed temperature setpoint and the programmed humidity
setpoint have been reached, even if the programmed heating time has
already elapsed.

LOOP

Ramp repeat function
The set programme is repeated after passing through all programmed
segments.
1-99

= repeats

cont

= continuous repeat function

HOLD

End of programme without switching off the heating and the humidifying
system.

END

End of programme, heating and humidifying system are switched off.

The programme segments are linked together by the segment closure command. These commands
therefore control the programme sequence.

Ramp

closure

command

ramp

segment 5

end

segment 5

°C

t=time

delayed

programme start segment 1

closure

command

ramp

segment 1

spwt (t)

segment 2

closure

command

ramp

segment 2

next

segment 3

closure

command

ramp

segment 3

spwt (tH)

segment 4

closure

command

ramp

segment 4

next