Installation check

5

58

EDKCSEK002 DE/EN/FR 2.0

5

Installation check

After completing the installation, check ...

ƒ

the wiring for completeness, short circuit, and earth fault.

ƒ

the power connection (X23):

polarity of the DC-bus voltage supply via terminals +UG, -UG

ƒ

the control connection (X26):

short-circuiting of the charging current limitation depending on the
power supply module connected.

Note!

In the next step the drive system is commissioned.
Relevant information can be found in the detailed documentation
of the power supply modules and axis modules connected.