In a tower configuration, leave at least a 7.6-cm (3-in) clearance space at the front and back of the server

for proper ventilation.
Rack server
To allow for servicing and adequate airflow, observe the following space and airflow requirements when

deciding where to install a rack:

Leave a minimum clearance of 63.5 cm (25 in) in front of the rack.

Leave a minimum clearance of 76.2 cm (30 in) behind the rack.

Leave a minimum clearance of 121.9 cm (48 in) from the back of the rack to the back of another
rack or row of racks.

HP servers draw in cool air through the front door and expel warm air through the rear door. Therefore,

the front and rear rack doors must be adequately ventilated to allow ambient room air to enter the

cabinet, and the rear door must be adequately ventilated to allow the warm air to escape from the

cabinet.

CAUTION:

To prevent improper cooling and damage to the equipment, do not block the

ventilation openings.

When vertical space in the rack is not filled by a server or rack component, the gaps between the

components cause changes in airflow through the rack and across the servers. Cover all gaps with

blanking panels to maintain proper airflow.

CAUTION:

Always use blanking panels to fill empty vertical spaces in the rack. This

arrangement ensures proper airflow. Using a rack without blanking panels results in improper

cooling that can lead to thermal damage.

The 9000 and 10000 Series Racks provide proper server cooling from flow-through perforations in the

front and rear doors that provide 64 percent open area for ventilation.

CAUTION:

When using a Compaq branded 7000 Series rack, you must install the high

airflow rack door insert [P/N 327281-B21 (42U) or P/N 157847-B21 (22U)] to provide

proper front-to-back airflow and cooling.

CAUTION:

If a third-party rack is used, observe the following additional requirements to ensure

adequate airflow and to prevent damage to the equipment:

Front and rear doors—If the 42U rack includes closing front and rear doors, you must allow

5,350 sq cm (830 sq in) of holes evenly distributed from top to bottom to permit adequate

airflow (equivalent to the required 64 percent open area for ventilation).

Side—The clearance between the installed rack component and the side panels of the rack
must be a minimum of 7 cm (2.75 in).

Temperature requirements

To ensure continued safe and reliable equipment operation, install or position the system in a well-

ventilated, climate-controlled environment.
The maximum recommended ambient operating temperature (TMRA) for most server products is 35°C