5verification and commissioning – KROHNE OPTISONIC 7060 EN User Manual
Page 42
OPTISONIC 7060
Electrical & mechanical installation manual 730962.31.00 page 42 of 52
5
Verification and Commissioning
5.1 Verification
5.1.1
Examining the condition
The following conditions must be fulfilled before you can start the verification procedure for
the
OPTISONIC
7060:
o
CONVERTER: Make sure there is no visible sign of damage, in particular to the sealing surfaces
and the internal contours of the connection flanges.
o
The meter body must be approved for the max. test pressure that is to be applied.
5.1.2 Testing
the
functions
Check that the OPTISONIC 7060 is properly installed mechanically and electrically, as detailed
in Section 3, to ensure successful commissioning.
The major system parameters have been configured at the factory. The default settings
should allow trouble-free operation of the ultrasonic gas flow meter.
Checking without PC and MEPAFLOW IV control and diagnosis software
The information listed below is shown directly on the LCD of the OPTISONIC 7060 (for details
on the menu structure and operation with a magnetic pen, see chapter 4).
5.2 Commissioning
5.2.1 Installation
Install the OPTISONIC 7060 in the line at the measurement position after completion of the
calibration. The necessary working steps are detailed in Section 3. Observe the safety
instructions
provided
in
that
Section.
5.2.2
Checking the functions
The current values of the operating volume counters (forward and reverse) are shown on
the
LCD
(see
Appendix,
Section
6.2.2
). If these values are displayed continuously, the
OPTISONIC 7060 is working correctly. A flashing display indicates a warning state or fault, which
should be analysed as described in Section 6.
Fasten the magnetic pen which is part of the measuring system and which is used to
operate the LCD on the CONVERTER using the strap provided on the OPTISONIC 7060 so that it
cannot be lost.