OPTISONIC 7060

Electrical & mechanical installation manual 730962.31.00 page 42 of 52

5

Verification and Commissioning

5.1 Verification

5.1.1

Examining the condition


The following conditions must be fulfilled before you can start the verification procedure for

the

OPTISONIC

7060:

o

CONVERTER: Make sure there is no visible sign of damage, in particular to the sealing surfaces

and the internal contours of the connection flanges.

o

The meter body must be approved for the max. test pressure that is to be applied.

5.1.2 Testing

the

functions


Check that the OPTISONIC 7060 is properly installed mechanically and electrically, as detailed

in Section 3, to ensure successful commissioning.

The major system parameters have been configured at the factory. The default settings

should allow trouble-free operation of the ultrasonic gas flow meter.


Checking without PC and MEPAFLOW IV control and diagnosis software

The information listed below is shown directly on the LCD of the OPTISONIC 7060 (for details

on the menu structure and operation with a magnetic pen, see chapter 4).


5.2 Commissioning

5.2.1 Installation

Install the OPTISONIC 7060 in the line at the measurement position after completion of the

calibration. The necessary working steps are detailed in Section 3. Observe the safety

instructions

provided

in

that

Section.

5.2.2

Checking the functions


The current values of the operating volume counters (forward and reverse) are shown on

the

LCD

(see

Appendix,

Section

6.2.2

). If these values are displayed continuously, the

OPTISONIC 7060 is working correctly. A flashing display indicates a warning state or fault, which

should be analysed as described in Section 6.

Fasten the magnetic pen which is part of the measuring system and which is used to

operate the LCD on the CONVERTER using the strap provided on the OPTISONIC 7060 so that it
cannot be lost.