3.4 Electrical

Installation


3.4.1 General

information

Pre-requisites

Wiring work (laying and connecting the power supply and signal cables) as a part of installing

the gas flow meter is not included in the scope of delivery. The mechanical installation

described in Section 3.3 must be completed. Comply with the minimum requirements of the

cable specs in accordance with Section 3.4.2.


Notes on cable laying

• Cables shall be laid in conduits or on cable trays to provide protection from mechanical

damage.

• Observe the permitted bending radiuses (generally, min. six times the cable diameter for

multi-lead

cables).

• Connections outside of conduits shall be as short as possible.

Warning

• Always observe the general safety regulations and safety instructions given in Section 1

when carrying out any installation work.

• Installation work shall only be carried out by trained staff and in accordance with the

relevant regulations issued by the operating company.

• Take appropriate measures to avoid potential local or plant-specific dangers.

3.4.2

Cable specs


Power supply 12 … 24 V DC

Specification

Notes

Type of cable

Tow leads

Connect shielding (if present) to
ground terminal

Min./ max. cross-
sectional area

0.5 mm² / 1.5 mm²

Maximum cable length

Depending on loop resistance; min.
input voltage at the OPTISONIC 7060:
12 V

Peak current 150 mA

Cable diameter

6 ... 12 mm

Fixing range of the cable glands




Digital output / current output

Specification

Notes

Type of cable

Twisted pair, shielded

Connect shielding at other end to
ground terminal

Min./ max. cross-
sectional area

2 / 0.5 mm²

Do not connect unused lead pairs
and prevent them form accidental
short-circuit.

Maximum cable length

Loop resistance under load ≤ 250 Ω

Cable diameter

6 ... 12 mm

Fixing range of the cable glands

WARNING