Installation, A-10 – Lincoln Electric IM10022 POWER WAVE AC_DC 1000 SD User Manual
Page 19
A-10
INSTALLATION
POWER WAVE
®
AC/DC 1000
®
SD
A-10
SINGLE ARC SYSTEM CHECKLIST (See Figure A.6)
Place the Power Wave
®
AC/DC 1000
®
SD in a suitable operating location.
Mount MAXsa™ 10 Controller.
Install MAXsa™ 22 Wire Drive and other accessories in their operating location.
Connect K2683-xx Heavy Duty ArcLink Control Cable (5 pin) between Power Wave and MAXsa™ 10.
Connect K1785-xx Wire Feeder Control Cable (14 pin) between the MAXsa™ 10 and the MAXsa™ 22.
Install Electrode Sense Lead (67) at the feeder and the Work Sense Lead (21) from the Power Wave
®
AC/DC
1000
®
SD per recommended guidelines.
Connect / Install welding cables per recommended "Output Cable Guidelines" (Table A.1).
Open the Power Wave
®
AC/DC 1000
®
SD front panels and check the DIP switch settings per the decal on the
panel. Factory Setting is “Master-Lead”. (See Figure A.4).
Connect input power to Power Wave
®
AC/DC 1000
®
SD per recommended guidelines.
Turn on Power Wave
®
AC/DC 1000
®
SD, and verify all system Status Lights are solid green.
Confirm that latest software is updated in all equipment prior to installation (www.powerwavesoftware.com)
Select a Welding process and configure starting and ending options.