beautypg.com

Kasco Marine Pond Aerator & Water Circulator User Manual

Page 13

background image

13

building, or other reliable means. This structure must

support the panel and prevent movement/flexing of the

panel. Use #10 x 1” or longer screws in the mounting

points of the control panel to secure to the post structure.

NOTE: The control panel must be hung upright in order to

be waterproof. It is also advised to mount the panel out of

direct sunlight if possible. Mounting the panel in a North

direction will prevent heat buildup inside the panel. Also,

mount the panel above the potential flood plain to prevent

water entry during a possible flood event.

STEP TWO

Set Timer in the control panel to desired ON and OFF times

per the Instructions for each specific timer.

STEP THREE

Follow all local and national electrical codes for this

installation and Consult a qualified electrician or service

person if needed.

(For 120V Installations)

Plug the aerator cord into the C-25 outlet labeled “UNIT”.

If lights are included, plug the Transformer cord into the

C-25 outlet labeled “LIGHT”. Now you are ready to plug

the C-25 into the 120V power supply on the post and EN-

JOY YOUR NEW KASCO AERATOR!

3 Phase: (2.3, 3.3, 5.3)

Refer to your 3 phase control panel instructions

Single Phase: (3400H, 4400H, 8400, 3.1, 5.1)

STEP THREE (For 240V Installation)

All electrical connections to this panel must be made

with proper strain relief cord grip fittings or with conduit

connections as required by local and national electric codes.

The bottom of the enclosure is reserved for field installation

of these connections.

C85 / C95 non-metallic control panel:

Incoming power connection: (Power feed)

This control panel requires a 240V or 208V - 4 wire service

(L1, L2, N, & G) and must be fed with a power circuit

protected by a circuit breaker or a fused disconnect switch

to provide circuit protection and a disconnection means.

C-85 panel requires at least a 30amp protected circuit

feeding the panel.

C-95 panel requires at least a 40amp protected circuit

feeding the panel.

Connect your power feed as detailed in the wiring diagram

provided with this panel.

L1 connects to Terminal

#1

L2 connects to Terminal

#2

N connects to Terminal N

G connects to Terminal GROUND - located on

chassis

plate

Be sure to provide adequate sized power conductors

to prevent excessive voltage drop. Consult with your

electrician to properly size power feed conductors. Use

copper conductors only.

Aerator power cord connection:

Your aerator (pump) will be provided with a flexible power

cord for connection to this control panel. If the power cord

has a plug, you will need to cut it off. The power cord

conductors (black, white, green) will need to be stripped

back 1/2”. The outer black jacket should be stripped

back at least 3inches. Follow the connection diagram for

terminating these three wires to the terminal blocks in the

control panel.

Black connects to Terminal

#4

White connects to Terminal

#5

Green connects to Terminal

G

Light Kit connection:

If you purchased a Kasco light kit(s) for your aerator,

follow the light kit installation instructions for mounting

the light kit(s) to the aerator float.

This control panel requires a hardwire connection for

the light kit(s). To connect the light kit(s) you will need

to cut off the power cord plug that is molded to the light

kit power cord. Strip back the black outer jacket of the

light kit power cord at least 3inches to reveal the three

internal wires of the power cord. (black, white, and green

conductors). These three wires will need to be stripped

back 1/2”. Follow the connection diagram for terminating

these three wires to the terminal blocks in the control panel.

Light kit connections:

Black connects to Terminal

#6

White connects to Terminal

#7

Green connects to Terminal

G

STEP FOUR:

Test the GFCB with the test button now and every 30

days.

If lights are installed, they can now be installed per Instruc-

tions included with the lights.

Once completed, power can be restored to the panel.