FIGURE 5 - CONDENSATE DRAIN PIPING FOR VANTAGE BOILERS
Figure 5 Notes:
Header must be level or slightly pitched toward the drain.
Header material to be galvanized steel or 316L stainless.
Header should be taken to the lowest point possible and
at least 5.5 inch (14.2 cm) drop from 1.5 inch (38.1 mm)
condensate drain kit/trap outlet.
1.5 inch (38.1 mm) condensate drain kit/trap outlet is never
to be above 1 inch boiler condensate outlet.
For multiple boiler installation, maintain and minimum pipe
size of 1 inch (25.4 mm) for the header piping.
The maximum number of units to attach per condensate
drain kit is 12mm BTU total.
Detail A
0.25” (U.S.) TAPPING
PROVIDED FOR WATER
CONNECTION TO MAINTAIN
WATER SEAL
5.5 INCH (14.2 CM)
MINIMUM
SIDE VIEW
Detail A