DAILY START-UP

INNOVATOR MEGAJECT

ACTIVITIES MUST BE DONE IN THE SEQUENCE SHOWN, AND MUST BE TICKED OFF AS
COMPLETED. THIS SEQUENCE FOLLOWS ON FROM “FIRST TIME START-UP CHECKLIST”

ACTIVITY

NO.

ACTIVITY

TICK WHEN
COMPLETED

Priority

Put on Respirator as specified for spray painting, Protective Clothing,
Eye Protection, and PVC Gloves

1

Check all hoses for damage.

2

Check all material supplies and fill or replace as needed.

3

Open main air supply slide valve on the back of the control box.

4

Press the recirculation button and allow the unit to recirculate for at least 20
strokes or until no bubbles are seen returning to the catalyst jug from the
recirculation tube.

5

Check that the catalyst percentage is set properly

6

Check resin pump pressure and adjust as necessary.

7

Check the MPG set pressure and adjust as necessary.

8

Set the desired number of counts on the Counter Display.

9

Press the Stop button to take the unit out of recirculation mode.

10

It is always a good idea to do a gel test each morning and balance the fluid
pressures. So place the appropriate container under the injection head and
press the Inject button and pump 2 or 3 strokes. Then press the Stop button.

11

Press the Reset button on the Counter to reset the counter to zero.

12

Flush the injection head as necessary.

13

The unit is ready to inject a part – connect the injection hose to the injection
head and press the Inject button. If using a TAS (Turbo Autosprue), PPVS
or other options properly connect the control line to the control box.

14

When the injection is complete press the Reset button on the counter and
connect to the next part or flush.

15

Flush the injection head as necessary.


ABNORMAL CONDITIONS OBSERVED AND CORRECTED

Abnormal Condition

a

a

a

a when
corrected


OPERATORS NAME

_______________________________

DATE:

_____________


SIGN OFF WHEN START UP CHECKS ARE COMPLETED:

__________________________



This manual is related to the following products: