Magnum Venus Plastech UltraMAX Shut-Down Checklist User Manual
Ultramax™ shut-down checklist
ACTIVITIES MUST BE DONE IN THE SEQUENCE SHOWN, AND MUST BE CHECKED OFF AS COMPLETED. USE
THIS CHECKLIST IN CONJUNCTION WITH THE OPERATING MANUAL FOR THE ULTRAMAX UNIT. THIS
SEQUENCE FOLLOWS ON FROM
“SET-UP FOR FIT
®
CHECKLIST.
ABNORMAL CONDITIONS OBSERVED AND CORRECTED
Abnormal Condition
when
corrected
OPERATORS NAME _______________________________________ DATE: ________________
SIGN OFF WHEN SHUT DOWN CHECKS ARE COMPLETED : _________________________
UltraMAX™ Shut-Down Checklist
ACTIVITY
NO.
ACTIVITY
WHEN
COMPLETED
Priority
Put on Respirator as specified for spray painting,
Protective Clothing, Eye Protection, and PVC
Gloves
1
Flush the gun with solvent.
2
Wipe the face of the nozzle after flushing.
3
Turn off the main inlet air ball valve at the manifold.
4
Release the solvent flush tank pressure.
5
Remove the nozzle and clean it.
6
Remove the Mix Housing and clean it.
7
Wipe the gun block face with a clean rag.
8
Hang the gun with the gun block exit holes facing
down.
- PATRIOT 10:1 ADHESIVE SYSTEM (66 pages)
- PATRIOT PAT-CP-0550 (29 pages)
- PATRIOT 10 PAT-PH-10000 (34 pages)
- PATRIOT 7 PAT-PH-7000 Series (48 pages)
- PATRIOT 5 PAT-PH-5000 Series (42 pages)
- PATRIOT 4-1_4 PAT-PH-4250 (34 pages)
- PATRIOT 3-1_4 PAT-PH-3250 Series (36 pages)
- PATRIOT HV PAT-LS-49090 (33 pages)
- PATRIOT 1-3_4 PAT-LS-24050 (60 pages)
- PATRIOT 1-1_4 PAT-LS-12270 (66 pages)
- PATRIOT SS PAT-CCP-LS-0590-SS (30 pages)
- PATRIOT PAT-CCP-LS-0590 (42 pages)
- PATRIOT PAT-CP-3000 (28 pages)
- PATRIOT PAT-CP-1530 (32 pages)
- PATRIOT PAT-CP-0980 (29 pages)
- PATRIOT PAT-CP-0245 (32 pages)
- PATRIOT FIRST TIME START-UP CHECK LIST - Internal Mix (1 page)
- PATRIOT DAILY START UP - External Mix (1 page)
- PATRIOT DAILY START UP - Internal Mix (1 page)
- PATRIOT PRE-START CHECKLIST - External Mix (1 page)
- PATRIOT PRE-START CHECKLIST - Internal Mix (1 page)
- PATRIOT SET-UP - External Mix (1 page)
- PATRIOT SET-UP FOR CHARGEABLE - Internal Mix (1 page)
- PATRIOT Multi-Color Gel Coater MVE-PAT-1500-X (60 pages)
- PATRIOT TESTING & ADJUSTING (55 pages)
- PATRIOT DAILY SHUT DOWN CHECKLIST - External Mix (1 page)
- PATRIOT DAILY SHUT DOWN CHECKLIST - Internal Mix (1 page)
- PATRIOT SPRAY FAN SETUP - External Mix (1 page)
- PATRIOT SPRAY FAN SETUP - Internal Mix (1 page)
- PATRIOT FIRST TIME START-UP CHECK LIST - External Mix (1 page)
- UltraMAX VHPC-1100 Series (25 pages)
- UltraMAX VHPC-4200 Series (26 pages)
- UltraMAX VHPC-3200 Series (39 pages)
- UltraMAX VHPC-2200 Series (34 pages)
- UltraMAX VHPC-2000 Series (32 pages)
- UltraMAX VHPC-1200 Series (25 pages)
- UltraMAX VHPC-1000 Series (38 pages)
- UltraMAX MULTI–COLOR GELCOATER MVG-1400-X-1 (50 pages)
- UltraMAX MVP Installation & Set-Up (2 pages)
- UltraMAX Start-Up Checklist (1 page)
- UltraMAX Pre-Start Checklist (1 page)
- UltraMAX Start-Up Sheet Quick List Instructions (1 page)
- UltraMAX Installation (1 page)
- UltraMAX HVLS-1000 Series (40 pages)