Installing the cs 120p in a suspended, Ceiling — division of labor – Extron Electronics CS 120P User Guide User Manual
Page 21
Installing the CS 120P in a Suspended Ceiling — Division of Labor
In a division of labor installation, low-voltage contractors install the CS 120P enclosure
(construction rough-in phase).
NOTE: The ceiling grid must be installed before the installation of the CS 1226T can
begin.
•
Verify if fiberglass ceiling tiles are being used (see
•
The grid face must be at least 15/16 inch (24 mm) for proper installation of the
CS 120P (see
on page 19 for details on suspending the enclosure on a
smaller grid face).
Side View
15/16" (24 mm)
Grid Face
Figure 24.
Grid Face Example
Use the following procedure:
1.
Disconnect power
—
Power down all attached devices before proceeding.
2.
Verify the space where the system will be installed — Ensure that there is sufficient
clearance above the ceiling tile for the unit to be installed.
3.
Configure the CS 120P for a U.S. or metric ceiling grid — For U.S. ceilings (2 feet
by 2 feet or 2 feet by 4 feet), leave intact the four tabs that are on one of the short ends
of the enclosure.
For metric ceilings (600 mm by 600 mm or 600 mm by 1200 mm) cut off the tabs.
Tabs (4)
Removable
Tabs
Figure 25.
Tabs on the CS 120P
CS 26T and CS 120P User Guide • Installation