Creating a ZigBee network using the ZE10 modules consists of the following steps:
Install the ZE10 module on the development board
Create a ZigBee network by configuring a ZE10 module as the coordinator
Configure ZE10 modules as routers. This step is optional since the coordinator works as a router
too.
Configure ZE10 modules as end-devices
Transmit data between ZE10 devices
This chapter describes how to install the ZE10 modules on to the development boards and how to use
terminal software programs to access the ZE10 modules using AT commands for configurations and
operations. The rest of the steps including ZigBee network creation, coordinator/router/end-device
configurations and data transmissions are described in the following chapters. The more detailed
information on the starter kit and the configuration examples are also provided in the later chapter.
2.1
Hardware Installation
2.1.1
Development Board Layout
Figure 2-1 shows the layout of the development board. The development board provides the interface
between the ZE10 and the external serial port or USB port together with input/output terminals for
convenient tests.
Figure 2-1 Development Board Layout