7. Sidedraw Accessory Instructions

PNEG-2400 CFL Commercial Farm 4" Corrugation Externally Stiffened Grain Bin

77

Sidedraw System Installation (Continued)

Locating Chutes

1. Starting from the first row of holes in the top sheet, measure down the “starting distance” for the bin.

(See

Sidedraw Chute Chart on Page 76.

)

(See Figure 7C on Page 76

and

Figure 7D below.)

2. Keep adding the required number of chutes, making sure to leave 8" between the chute bolt holes.

(See Figure 7C on Page 76.)

3. Stagger the sidewall sheets on three (3) post stiffened tanks to create a vertical strip between

stiffeners free of vertical seams. Install the chutes between the stiffeners in this area.

Locate Discharge Opening

1. The last bolt hole in the chute should line up with the center of the discharge chute opening that is to

be cut.

(See Figure 7E.)

Approximate an opening by measuring 9-1/2" above and below the last bolt

hole of the chute. Mark horizontal cut lines.

2. To find the vertical center of the chute opening, measure over 11" to the right and left of the chute

bolt rows. Mark center point.

(See Figure 7E.)

Measure 7" from the center point on both sides and

mark vertical cut lines.

3. Cut opening where marked, making sure corners have a minimum of 1-1/2" radius.

(See Figure 7E.)

Figure 7D

Figure 7E