3. Bin Assembly
PNEG-2400 CFL Commercial Farm 4" Corrugation Externally Stiffened Grain Bin
43
Installing the Seal Weldments
The seal weldments are located along the top and bottom of the door frames and function as a barrier,
keeping weather from entering the bin and grain from exiting the bin.
1. Locate outside seal weldment (NCWT0383) along the top of the outer door frame weldment
(NCWT0380 for triple punched frame and NCWT0407 for double punched frame). Fasten to top
of outer door frame using bolts (S-277) and washers (S-10102).
2. Locate inside side seal weldment (NCWT0436) along the top of the inner door frame weldment
(NCWT0381 for triple punched frame and NCWT0408 for double punched frame). Fasten to top of
inner door frame using bolts (S-277).
3. Fasten both top seal weldments simultaneously to the sidewall sheet using bolts (S-3727) and
nuts (S-456).
4. Repeat
for the bottoms of the inner and outer door frames.
Installing the Kick Plate
The kick plate gives a uniform surface for entering the bin and covers the gap between the inner and
outer doors.
To Install the Kick Plate
1. Standing at the outside of the bin looking into the door, place the kick plate (NCWT0376) into the
doorway with the wider side to the inside of the bin.
2. Place the front lip of the kick plate into the recess of the outer door frame.
Figure 3AB Kick Plate in Recess of Outer Door Frame