beautypg.com

Sidedraw system installation, Wind ring installation – Grain Systems Tanks PNEG-2400 User Manual

Page 73

background image

7. Sidedraw Accessory Instructions

PNEG-2400 CFL Commercial Farm 4" Corrugation Externally Stiffened Grain Bin

73

1" Diameter Anchor Bolt Requirements for Sidedraw Systems

1" Diameter Anchor Bolt Requirements for Sidedraw Systems Installed in
CFL - 4" Corrugation Commercial Tanks

2 Post Tanks (2 Stiffener per Sidewall Sheet)

3 Post Tanks (3 Stiffener per Sidewall Sheet)

Sidedraw System Installation

Wind Ring Installation

1. Sidedraw systems may require additional wind rings. They will need to be attached at the

beginning of assembly because they go on the upper most rings. (See wind ring requirements

chart

on Pages 74 and

75

.)

2. Attach the wind ring pipe to the stiffeners using 3/8" x 1" bolts through the flange of the stiffener.

(See Figure 7A.)

In some cases field drilling of wind ring locations may be required.

3. Attach wind ring pipe section to the stiffener using two (2) 3/8" x 6" (S-7248) wind ring clamps.

(See Figure 7A.)

4. Place pipes end to end without overlapping. Fasten together using two (2) wind ring couplers and

six (6) 3/8" x 1" flanged head bolts with nuts. Couplers should be centered on the seam of pipes.

(See Figure 7A.)

Figure 7A

Nominal Tank Diameter

Total Number of Anchors

54

36

60

40

Nominal Tank Diameter

Total Number of Anchors

54

54

60

60