4. Assembly

20

PNEG-1049 10"-12" Commercial Bin Sweep Augers

13. Bolt the shield splice plate to complete the connection of the two (2) back shields. Use four (4)

5/16" x 3/4" hex bolts, flat washers and serrated flange nuts.

(See Figure 4L.)

Figure 4L Shield to Shield through Splice Plate

14. Repeat

Step 8 on Page 18

through

Step 11 on Page 19

.

NOTE: Bin sweeps with three (3) or more flight and shield sections use a carrier wheel assembly

after every two (2) sections. The first carrier wheel assembly should be installed after the first
two (2) sections of flight and shield.

15. Place the carrier wheel assembly over the bearing stand assembly. Attach the previous and next

sections of back shield to the carrier and bearing stand assembly using two (2) 3/8" x 3-1/2" hex bolts,
four (4) flat washers and two (2) nylock nuts.

(See Figure 4M.)

Figure 4M Shield to Shield through Carrier and Bearing