Dump hopper installation floor sheet installation, Dump hopper installation, Floor sheet installation – Grain Systems PNEG-1510 User Manual
Page 42: Installation
8. Installation
42
PNEG-1510 Top Dry 24', 30' and 36' Manual Batch
Dump Hopper Installation
Pre-assemble the dump hoppers, dump brackets and flashing angles to the floor sheets. Place a dump
hopper under the floor sheet and align it with the pre-punched large hole. Place a flashing angle on top of
the sheet across the outer edge of the hopper entrance with the interior of the angle facing the sidewall.
Screw down through the angle, sheet and hopper with 5/16" x 3/4" self-tapping screws.
Figure 8E
Floor Sheet Installation
Now the assembled sheets can be placed over the rafter framework. As the sheets are placed and
overlapped they are to be screwed down to the rafters using 5/16" x 3/4" self-tapping screws, leaving the
third and eighth holes empty.
Figure 8F
Nominal Diameter
of Tank (Ft.)
# of Holes to Leave Empty
24'
Third and Eighth Holes
30'
Fourth, Seventh and Tenth Holes
36'
Third, Sixth, Tenth and Twelfth Holes