Figure 26. Ceiling Firestop (Ceiling Side)

If the area above the ceiling

IS an attic, position and secure

the firestop on top of the previously framed hole.
NOTE: Keep insulation away from the vent pipe at least

1 inch (25mm).

Figure 27. Attic Firestop

JOIST

CEILING FIRESTOP

CEILING

NAILS (4 REQUIRED)

CEILING

CEILING FIRESTOP

RAFTER

NAILS (4 REQUIRED)

NOTE: There must be NO INSULATION or other

combustibles inside the framed firestop opening.

Figure 28. Trapezoid Termination Cap

!

C. Vent Termination

Refer to Cinch Pipe and Termination Cap installation in-

structions.
Horizontal Termination
• The termination kit should pass through the wall firestops

from the exterior of the building.

• Adjust the termination cap to its final exterior position

on the building and interlock the flue sections.

!

WARNING: VENTING TERMINALS SHALL

NOT BE RECESSED INTO A WALL OR SID-

ING. VENT TERMINATION CLEARANCES MUST

BE FOLLOWED TO AVOID FIRE DANGER. SEE

VENT TERMINATION MINIMUM CLEARANCES DI-

AGRAM ON FOLLOWING PAGE.

WARNING: THE TERMINATION CAP MUST BE

POSITIONED SO THAT THE ARROW IS POINT-

ING UP.

7-1/4 in.

(184mm)