Installation and assembly, Side chute assembly – MCZ Vivo 90 Pellet Comfort Air User Manual
Page 28

50
MIN.
590
431
800 MAX
705 MIN
800 MAX
705 MIN
165
440
230
933
500*
50
MIN
230
933
500*
26
7-INSTALLATION AND ASSEMBLY
SIDE CHUTE ASSEMBLY
In the event of opting for side chute installation, the distance from the machine axis to the wall must be 80 cm maximum (picture on the
side).
To position the chute, proceed as follows:
• Connect the pipe supplied to Vivo 80 Pellet ensuring it is rotated to the side, and fasten it with the clamp.
• Connect the pipe (in the top section) to the mouth of the hatch structure by means of the clamps supplied.
• Position the pipe with the hatch structure so that, when cladding is completed, it may be screwed and fixed to the wall of the
cladding at the hole made to insert it.
• To mount the outer hatch refer to the suitable paragraph, since this operation is to be performed with completed cladding.
SIDE CHUTE ASSEMBLY
*MINIMUM OPTIONAL SUPPORT HEIGHT