Retrofit Installation

40

9.6

Emerson Network Power (CEMS100 / LECS15)

The kit includes a special cable to allow simple interconnection

between the controller and the OpenComms NIC.
Questions about the retrofit kits should be directed to the Interna-

tional Sales department.
Contact:

[email protected]

9.7

UPS Installation

Retrofit kits are designed specifically for individual units. Consult

your local sales / service representative for pricing, part numbers and

installation help.

9.8

Npower

As a minimum there will be an IFM board (communications interface)

mounted at the mid-point on the door. Other options may also have

been previously installed.
The Option boards mount on the inside of the option door. Options can

be located in any available option slot, however the OpenComms

NIC should be mounted in the bottom most (bottom cable entry) posi-

tion.

9.8.1 Power Connection for NPower

After mounting the NIC card in the uppermost or lowermost option

position, per the instructions above, route the wire harness from TB3

on the lower left of the NIC card to the power supply board on the back

of the control door. Follow the routing path indicated in Figure 7.

9.8.2 Communication Connection for NPower

Connect the 2-wire harness from TB1 on the bottom center of the NIC

card to TB55 on the IFM card. The board is now ready to connect cus-

tomer inputs, which should be routed from either the top or bottom

cable entry points.
Refer to the NPower option manual for any further details on installa-

tion.
See Figure 15 for single line detail.