3.0 Installation
© 2011 Magnum Energy, Inc.
44
IMPORTANT: Coordinate the DC wiring to each inverter from each DC breaker such that the
far left inverter (Master)is connected to the far left breaker (Master DC breaker), and the sec-
ond inverter (Slave) is connected to the second DC breaker (Slave 1 DC breaker), and so on.
MPXD-30D DC Wiring
This section covers the DC wiring to/from the inverters, and from the battery bank.
WARNING: During normal operation, the terminals, busbars, and electrical components
inside the MP enclosure may be energized – DO NOT TOUCH.
WARNING: Disconnect all power sources before removing the cover. Even though DC
voltage is “low voltage”, signifi cant hazards may be present, particularly from short cir-
cuits of the battery system.
CAUTION: DO NOT connect the battery cables to the battery bank until all wiring to the
inverters and inside the MP/MPX enclosure is complete and the correct DC voltage and
polarity have been verifi ed.
Installing the DC Cables From the Inverters to the MP (see Figure 3-22c)
1. Route a DC positive cable (red) from each inverter into the MP enclosure.
2. Connect the end of the DC positive cable (red) to the inverter’s positive DC terminal.
3. Connect the other end of the DC positive cable (red) to a DC circuit breaker’s top terminal.
4. Route a DC negative cable (black) from each inverter into the MP enclosure.
5. Connect the end of the DC negative cable (black) to the inverter’s negative DC terminal.
6. Connect the other end of the DC negative cable (black) to the top of the DC shunt’s busbar.
7. Route an appropriately sized DC equipment ground wire from each new inverter’s DC GROUND
terminal to the DC GROUND busbar in the MP enclosure.
8. Verify all DC connections are torqued from 10 to 12 ft lbf (13.6 to 16.3 N-m).
9. Once the DC connections are correctly wired and tested, coat the terminals with an approved
anti-oxidizing coating.
Installing the DC Cables From the Battery Bank to the MP Enclosure (see Figure 3-22d)
WARNING: Ensure all AC and DC breakers are switched OFF before connecting or disconnecting
the battery cables, and that all AC and DC power is disconnected from the inverter.
WARNING: Lethal currents will be present if the positive and negative cables attached
to the battery bank touch each other. During the installation and wiring process, ensure
the cable ends are insulated or covered to prevent touching/shorting the cables.
CAUTION: The Magnum inverter is NOT reverse polarity protected, if this happens the
inverter will be damaged and will not be covered under warranty. Before making the
fi nal DC connection
from the MP enclosure down to the battery bank, verify the correct
battery voltage and polarity by using a voltmeter. If the positive (+) terminal of the bat-
tery is connected to the negative
(–)
busbar of the MP enclosure and vice versa, severe
damage will result. Ensure the cables are color-coded to avoid polarity confusion.
1. Route a DC positive battery cable (red) from the battery bank through the bottom of the MP
enclosure for each inverter.
2. Connect the end of the DC positive battery cable (red) to the DC circuit breaker’s bottom
battery positive connection.
IMPORTANT: Damage may occur if DC power is connected to the MP enclosure before the
Communication wiring is completed. DO NOT connect the DC cables from the MP enclosure
to the battery bank until: 1) all DC, AC, and Comm wirings are completed, 2) the correct DC
and AC overcurrent protection have been installed and, 3) the correct DC voltage and polarity
have been verified.