6  Electrical Connection

SMA Solar Technology AG

26

MC-BOX-12-3-20-BE-en-10

Operating Manual

6.10 Connecting the Data Cables for Measurement Signals and

Communication

The data cables for measurement signals and communication are connected on the SIBUCTRL.

Figure 13: Overview of the connection area in the SIBUCTRL

Procedure:

1. Insert the data cables into the Multicluster Box (see Section 9.3.2, page 32).
2. Connect the data cables for measurement signals (red):

• for the master of the main cluster to pin connector X30 (Mstr/L1 BackupVtgCur)
• for slave 1 of the main cluster to pin connector X31 (Slv1/L2 BackupVtgCur)
• for slave 2 of the main cluster to pin connector X32 (Slv2/L3 BackupVtgCur)

3. Connect the data cable for communication between the Sunny Island inverters and the Multicluster Box (black) to

pin connector ComSyncIn.

4. Connect the other end of the data cable to pin connector ComSyncIn of a Sunny Island inverter in the main cluster.

Since all Sunny Island inverters of the main cluster (master and slaves) are interconnected via a communication bus,

the Multicluster Box can be connected to a slave or to the master of the main cluster (see documentation of the

Sunny Island inverter).

5. Ensure that the terminator is plugged into the pin connector ComSyncOut.

6.11 Mounting the Kick Plates

Requirement:

☐ All installation work must be completed.

Procedure:

1. Ensure that the power cables are retained with a strain relief.
2. Insert the kick plates and attach with the fastening screws (TX 30, torque: 21 Nm).

Position

Designation

A

Pin connectors for measurement signals (ComSyncIn, ComSyncOut)

B

Pin connectors for communication (X30, X31, X32)